ODOT (Ohio Department of Transportation) is currently working on eastbound and westbound I-70 through Huber Heights and into Clark County. The construction work is located between I-75 and I-675. The work being performed includes the full-depth removal and replacement of sections of concrete pavement that have broken apart at the pavement joints. The majority of the repair work is being done in the right and middle lanes of the 3-lane roadway (both eastbound and westbound). The work began at the beginning of April and is scheduled to be completed by September 30, 2025. One or two lanes of roadway closure could occur at any time. The on and off ramps within the construction zone are expected to remain open at all times.
This is an ODOT project that is being managed and inspected by ODOT. The City of Huber Heights does not have any involvement in this project.
If you have any questions, comments, or concerns, please contact ODOT, District 7, at (937) 492-1141.