Brandt Pike at Chambersburg Road Mast Arm Installation

                                                       

January 21, 2020 - The City of Huber Heights will be making upgrades to the intersection of Brandt Pike and Chambersburg Road. The traffic signals at that location will be changed from the current pole wire supports to using pole and mast arm supports. The project was designed by The Kleingers Group and was placed out for bid last fall. Bansal Construction was the chosen contractor that was awarded the project last September. Since that time, they have submitted shop drawings for all of the materials that will be used on the project. Upon approval, the materials were ordered and there was a minimum three month waiting period for the delivery. There will be a pre-construction meeting in February and the contractor is schedule to being work in March. The project should take approximately 2-3 months to complete (weather permitting).