Sidewalk Program

Project Description


The 2020 Sidewalk Program consists of:


  • Removing and replacing sidewalk and aprons
  • Raising and settled section of concrete sidewalks and aprons by mud jacking them to the correct grade
  • Removing and replacing marked sections of concrete curb and gutter, replacing catch basin aprons, and reconstructing curb ramps. 
  • Installing 8’ wide sidewalk on the north side of Chambersburg Road east of Owens Drive

Section A is a replacement of concrete, sidewalks, and aprons; Section B is sidewalk blocks raised; Section C is the concrete portion of the street program. 


2020 Sidewalk Program Map 


Contractor

  • Section A- Multi-Task Construction
  • Section B - A-1 Leveling
  • Section C - Multi-Task Construction